- GROUP COMPANY: J/V ERETBO S.A. - EKTER S.A. - DOMIKI KRITIS S.A.
- CLIENT: ORGANIZATION FOR THE DEVELOPMENT OF CRETE (ΟΑΚ S.A.) / DIRECTORY OF TRANSPORTATION PROJECTS
- VALUE (€): 47.000.000,00 €
- LOCATION: CRETE
- START-COMPLETION: 26/10/2016 - 27/08/2020
- STATUS: COMPLETED
- DESCRIPTION:
The forseen project works from the start (Sta. 22+170) until the end (Sta. 29+990) consost of the following section:
- Excavation B01 (Sta. 22+170 - Sta. 22+635)
- Sta. 22+635 - Sta. 23+065
- Excavation B04 (Sta. 23+040 - Sta. 24+205)
- Tunnel entrance excavation (Sta. 24+200 - Sta. 24+315)
- Ag. Varvara tunnel (Sta. 24+315 - Sta. 24+820)
- Tunnel exit mouth and Cut & Cover (Sta. 24+820 - Sta. 24+828,74)
- Ag. Varvara bridge (Sta. 24+840 - Sta. 25+100)
- Excavation B08 (Sta. 25+100 - Sta. 25+300)
- Excavation B09 (Sta. 25+300 - Sta. 25+500) - κατασκευή Lane & Cover
- Excavation B10 (Sta. 25+500 - Sta. 26+100) - κατασκευασμένο Lane & Cover
- Panasos flyover Excavation Β50 (Sta. 26+100 - Sta. 26+700)
- Constructed excavation Β13 (Sta. 26+700 - Sta. 27+065)
- Constructed ground instability bridge and constructed excavation Β14 (Sta. 27+065 - Sta. 27+540)
- Constructed excavation B15 (Sta. 27+540 - Sta. 28+085)
- Constructed bridge Apomarma Ι (Sta. 28+085 - Sta. 28+295)
- Constructed excavation B28.4 (Sta. 28+295 - Sta. 28+500)
- Excavation B40 Gergeris flyover (Sta. 28+500 - Sta. 28+850)
- Excavation B40 Gergeris flyover(Sta. 28+850 - Sta. 29+550)
- Constructed bridge Apomarma ΙΙ - end of road project (Sta. 29+550 - Sta. 29+999)
The estimated completion time of the project is 30 months.