PERIMETRIC COVERAGE OF OAKA OLYMPIC VELODROME –AIR CONDITIONING

1
  • GROUP COMPANY: ETBO S.A.
  • CLIENT: GENERAL SECRETARIAT OF SPORTS – DIRECTORATE OF SUPERVISION, CONSTRUCTION, & MAINTENANCE FOR SPORT PROJECTS
  • VALUE (€): 3.266.457,02
  • LOCATION: ATHENS
  • START-COMPLETION: 09/06/2006 – 26/10/2007
  • STATUS: COMPLETED
  • DESCRIPTION:

    The project involves the perimetric coverage of OAKA OLYMPIC VELODROME with a complex construction made of facades with double-glaze window panes and a solid metal facade. The project also included air-conditionning installations.