- GROUP COMPANY: ERETBO SA
- CLIENT: JACOBS SUCHARD PAVLIDES SA
- VALUE (€): 3.293.238,61
- LOCATION: ATHENS
- START-COMPLETION: 12/06/1998 – 15/04/2000
- STATUS: COMPLETED
- DESCRIPTION:
The project involves the following modernisation works JACOBS SUSHARD PAVLIDES factory: Industrial and building repairs, reconstruction of water supply, hydpaulic, drainage and rainwater networks, construction of waste water tratment, reconstruction of steam and compressed air network, air-conditioning-cooling -ventillation networks, substation networks of strong currents and special elevator fot industrial. The plant was in operation during the whole period that works were curried out.